We were instructed by one of our clients to carry out the large task of partially removing a 33-floor goods lift and the Lift machine replacement in a busy hotel in London. This site was a particularly challenging one to work on as Hilton Park Lane is one of London’s busiest hotels.
The brief
The first port of call was to install the 33 landing hoardings to make the work area safe and secure. Using the running lift the shaft was then painted, helping to seal it from dust and improve visibility for engineers, as well as making it easier to maintain.
Our engineers then used the running lift to remove all door and landing equipment, dismantling all entrances and clearing the steelwork from the site each time the lift car had reached its weight capacity; the process was then repeated for all backfill behind the architraves.
Once the counterweight was positioned on props, the car was tackled and de-roped, removing over 1200 metres of rope from the lift and disposing of it in the correct manner- being licensed waste carriers, our company are environmentally aware.
All redundant and waste metal was removed from the site and recycled, and all concrete was taken to the correct waste disposal site.
Our team then began on the works in the motor room, dismantling the large Otis gearless unit and bedplate which was then to be lowered down through two pre-cut trapdoors getting us down through the double plant room into the lift lobby.
The machine and bedplate were taken down in manageable pieces and removed from the site using the correct material handling equipment.
We then removed the large redundant diverter wheel from the wheel housing space between the lift motor room and lift shaft and removed this from the site.
The new TK elevator SC400 gearless machine unit and bedplate was then delivered to the site.
Using a mobile Gantry, we positioned the unit on a pallet truck and moved it round to the lift lobby where it was transported to the top floor. The large bedplate and diverter steelwork were then tackled up through both trapdoors and assembled.
Our team then tackled the new machine into position and fixed it in the correct position to pick up the car and counterweight centres.




Once the new machine had been roped, we then had a cantilever scaffold installed at the top floor which we used to walk out on and hang the counterweight in the top of the shaft. This allowed us to clamp the ropes and remove the redundant lift car and sling, and all redundant pit equipment.
Once the job was complete, a final clearance was carried out to ensure the site was left clean and tidy for the installation team to begin installing all new equipment.
Contact us today for a hiring quotation or to talk to us about our services. Get a free quote from us today by calling 01732 824647 or enquire below.
Trusted by the Best
"The team handled our elevator removal quickly and safely—couldn't have asked for a smoother process."
Jack always delivers 5-star service, great variation of equipment for hire and quick to deliver products.
Highly recommend ESL liftings, they’re quick to quote and supply equipment, they are my go to
Quick easy and reliable, competitive on price too
“I have been hugely impressed by the way each member of the Elevator Solutions team takes responsibility and accountability for their tasks at hand, whilst demonstrating a sense of duty to put the customer first.”
Managing Director PEW Electrical Distributors Ltd
Looking for reliable lift removal services or high-quality lifting equipment? Contact ESL Lifting for a free site survey and quotation. We aim to respond to all enquiries within 24 working hours.
ESL Lifting Gear is a company aimed at providing high quality Lifting Equipment to the Lift Engineering Industry.
Elevator Solutions Provides professional Lift Removal and Decommissioning as well as Lift Shaft Maintenance, Hoardings and Painting
© 2025 ESL Liftings. All Rights Reserved.
Website designed and built by Studio 77.